Inside the data center.

From the campus to the memory beside a chip. Open it up. See what each part does.

Explore a system
DATA HALLCONCEPTUAL MODEL · NOT TO SCALE

Assembling the model…

Drag to orbit · Scroll or pinch to zoom

Roof open. Select a rack to move closer.

A SIMPLE FACILITY SCENARIO

How much power supports the computers?

PUE compares total facility energy with IT energy. Change the assumptions to see the supporting overhead.

13.0 MWTotal facility power
● IT equipment 10 MW● Supporting overhead 3.0 MW

At a constant load for 8,760 hours: 113,880 MWh per year.

Illustrative steady-load calculation. PUE does not measure useful AI output or server utilization. Actual annual energy varies with load and operating conditions. Definition and source ↗

Conceptual teaching model. Shapes and connections are simplified. Parts separate only for explanation.